Bathroom renos: Day 15

3 03 2023

The skip bin people were here bright and early to take the very full (and heavy) skip. The electrician arrived just before 8:30 to do the final electrical work (power outlets, light switches, exhaust fans) and was done by about 10am. No more tradies until Tuesday (Monday is a public holiday here) when the painter arrives. The OM covered over the new shower fittings in prep for the painter.

Full skip ready to be taken away this morning. Bye-bye bathroom!

New exhaust fan above shower (there’s a similar one in the toilet). Both the PM and the electrician say these are incredibly efficient, far more so than the previous ones we had.

Plastic protective covering over the new shower fittings in readiness for the painter on Tuesday.

TWO double power outlets! We only had one before, on that far right wall. And a new hand-towel rail.

Boring but functional—light and fan switches; the 3rd switch in the toilet is for the smart toilet.





Bathroom renos: Day 14

3 03 2023

Posting these pics a little late as the plumber didn’t get here until late afternoon. Progress today installing the pelmets for the sliding doors and fitting and testing all the plumbing fixtures, including the toilet. 





Bathroom renos: Day 13

1 03 2023

The fittings are starting to go in—there’ll be more this afternoon, so I’ll add more photos at the end of the day.

Later…

Double shelves in the shower because we BOTH have shampoos etc. These were going to be side by side, but the position of the pipework behind the walls and the narrow gap for the shower hose meant that wasn’t a good option in reality (it looked good on paper, but sometimes you have to make compromises along the way, such as the position of the mixer tap for the shower—that was meant to be much closer to the window, but the hot water pipes for the whole house are behind the first set of tiles on that wall and the pipework for the shower and its tap cross those pipes so we couldn’t put the tap there without ripping out the whole wall (a load-bearing wall) and starting again—not going to happen!). Also a grab rail for holding onto when you clean your feet and between your toes.

Smart toilet facing the wrong way, but ready to be installed when the plumber comes tomorrow. Toilet roll holder still to be added, but grab rail already in place—remember, we want to ‘age in place’ in this house, so putting these things in now means we don’t have to retrofit if one of us has a temporary or long-term disability, or just needs a bit of support getting onto or off the toilet.

Double towel rails on the wall opposite the walk-in shower (DH is ~1.9 m tall, so the top one is for him!). If we need more towel rails, they can go on the back of the sliding doors (I’ve already checked this with the PM). Oh, and the vanity top, doors and handles have been added.





Bathroom renos: Day 12

28 02 2023

Today was the final tiling and all the wall and floor grouting. It’s now all drying in prep for tomorrow when some of the fittings and plumbing will start to get installed. It’s starting to look more and more like a bathroom!
Only the silicon beading to be done in the corners of the shower and where the wall tiles meet the floor.


Tiled floor has been washed and is now drying—the tiler did a great job matching the tiles in the channel drain with those on the floor. I watched him set aside those pieces several days ago when he was making his cuts for the floor tiles—that prep certainly paid off.

In this last photo, the grouted area is on the left showing how clean a finish grouting makes to the tiles; the ungrouted floor tiles are on the right. And my purple Crocs are making an unexpected appearance 🙂





Bathroom renos: Day 11

27 02 2023

The tiler and project manager (PM) here bright and early this morning. By lunchtime, the tiler had finished almost all the wall tiling, the PM made the surround for the in-wall toilet cistern, which the tiler mostly tiled. More time to cure, so they’d both left by lunchtime. The tiler will finish the last bits of tiling tomorrow and then do the grouting.

Later this week will see the return of the plumber and electrician, plus the painter, and most of the fittings will be installed. Next Monday is a public holiday, so the shower screen may not come until next Tuesday, but we should hopefully have a functioning bathroom sometime next week, a couple of days over the expected time. The doors won’t be installed until 14 March (I think), then I think the painter comes back to do those. And yes that now very yellow caramel paint will be replaced with a much lighter beach sand colour.





Bathroom renos: Day 10

24 02 2023

Almost 2 weeks into the 3-week reno (though it maybe a couple more days than that until it’s all finished). And by the middle of Day 10, we’re at the stage where all the floors have been tiled (not yet grouted) and the walls are partly tiled. I’ll add more photos at the end of the day.

Photos after the tiler finished for the day (I like how he tiled the floor and wall area that will be hidden by the vanity unit—it means that if we ever decide to change out the vanity, we won’t need to redo the tiling):





Bathroom renos: Day 9

23 02 2023

We have progress! The floor tiling has begun and is expected to be finished in a few hours. We’re getting floorboard-look tiles for the floor, in a soft caramel colour. Why? Because the wooden floors in our house are a honey-coloured blackbutt (Australian native timber) and the carpet in the adjoining bedroom is a caramel colour as are the walls etc. and I didn’t want to depart too far from what we already had.

I took a couple of photos when the tiler went to lunch. Possibly more to come later today. And yes, the shower will have a channel drain.

By 2pm, he’d finished the main bathroom floor except for a tiny bit in a corner and the toilet. The bathroom floor looks like that little Aussie bleeder, Norman Gunston (only Australians of a certain age will get that!)





Bathroom renos: Day 7 and Day 8

22 02 2023

Not a lot to report. The 3 coats of waterproofing need a day to dry between each coat, so the first few days this week is just watching paint dry—literally!

Both the tiler and the project manager have been here for short stints on both days—the tiler to do the waterproofing and prep work for tiling (which starts tomorrow, Day 9!) and the PM to do small things, like patch holes in walls then sand down in preparation for the tiling and painting, vacuum the concrete floors with an industrial-strength vacuum cleaner, replace skirtings on the bedroom side of the en suite that were taken off to allow the doorway to be widened etc.

And the tiler has put up his plan for the floorboard-style tiles he’ll be laying on the floor.

 





Bathroom renos: Day 6

20 02 2023

Day 6 of bathroom renos. Very quiet today. The only activity was the tiler doing the first waterproofing coat, and the project manager installing the architraves for the 2 widened doorways. Both were finished and gone before 11am.

Tomorrow will be another coat of waterproofing around 8am, with possibly the final (3rd) coat tomorrow afternoon if the weather remains hot and dry as expected. The Australian Standard for waterproofing is one coat up to 1.8 m high in the shower, but this company does 2 coats as standard and up to tile height (2 m in our case). Because I’ve had 3 bathrooms retiled in the past 16 years because of waterproofing issues, I insisted on 3 coats—I DO NOT want to have to be in a situation where this has to be redone.

Also, sometime in the past few work days, the cistern got installed inside the frame that will conceal it.

 





Bathroom renos: Day 5

17 02 2023

A very quiet day today. The PM and tiler both turned up early, and the tiler got on to filling and screeding the floor and wall area for the shower. But concrete (or whatever he uses) has to dry so he was done and gone by mid-morning. He’ll be back later today to do a bit more, then it will all dry over the weekend. He’ll start the waterproofing on Monday and that will take 3 days because I want 3 coats and up much higher on the walls than the Australian standard. He told me he’s not just waterproofing the shower area, but also the walls, floors and window ledges where water could splash, and the back wall where the bath used to be, and into the main bathroom area too. Each coat has to dry, so 3 coats = 3 days before he can start tiling. He can’t start tiling earlier from the toilet out otherwise he could be out in the measurements—the tiling has to start from the where the shower screen will go, which is why he can’t do anything until the waterproofing is all done. In my chat about our 3 previous experiences with bad waterproofing and bathrooms, I found that he and I are very much on the same page about getting the waterproofing done right the first time, because it’s way to expensive to fix later. An extra day for a 3rd coat? in the scheme of things, it’s a small price to pay.

The PM was also here first thing (it’s his day off!) and we pulled down the blue plastic that we’d had up to minimise the dust. He did a few things then took off for the day.